HISTORICAL BACKGROUND

Construction projects/Phases

The Limassol sewerage system has been constructed in phases and will cover the entire area under the Board, from Zakaki to Moni, including all the hotels in the area.

1st Phase

Work on the 1st Phase of the project began in May 1992 and was completed in early 1995.

2nd Phase

In the middle of 2004, in the framework of the expansion of the sewerage system, the Board completed its new investment programme for the 2nd Phase of the project (Phase 2a) which amounted to some €34 million. At the same time, a new investment programme (Phase 2b) was drawn up for the further expansion of the system at an estimated cost of approximately €325 million.

Phase 2a

Completed Projects

·         Sewerage projects

·         Expansion of the sewerage system

·         South of Spyros Kyprianou (previously Macedonia) Avenue, starting from the Linopetra area in a westerly direction as far as the crossing of Spyros Kyprianou (previously Macedonia) Avenue and Ayias Phylaxios Street.

·         All areas south of Archbishop Makarios III Avenue and Paphos Street, with Omonia Avenue as its western border.

Additional 1st Phase Sewerage Projects

·         Hotels area around Pyrgos and Moni

·         South of the Franklin Roosevelt Avenue area (Tsiflikoudia)

·         Other points within the 1st Phase where development has taken place since 1995

·         The pipes network from Ayia Zoni to Mesa Geitonia and the Spyros Kyprianou (previously Macedonia) Avenue network.

·         Additional works south of the ring road in the Linopetra area

·         Connection of the following government housing estates in Greater Limassol: Linopetra, Kapsalos, Makarios III, Ayios Athanasios, Tsiflikoudia and Omonia.

Storm Drain Projects 

These projects included the construction of separate pipes to carry rainwater to the sea and covered the following areas:

·         Costis Palamas Street and the Lanition High School area

·         Kolokotronis Street and Meletios Metaxakis Street – Mesa Geitonia area

·         Bizaniou Street – Ayios Athanasios/Yermasoyia area

·         Milton Street area

·         Omonia/Zakaki. As well as laying storm drain pipes in Milton Street, sewer pipes were also laid for future use.

·         Additional works on Spyros Kyprianou (previously Macedonia) Avenue

Phase 2b - Objectives

The Board has prepared a programme for further construction projects, aiming at the expansion and completion of all projects by 2018.

The objectives of Phase 2b may be summarised as follows: 

·         Expansion of the system, in particular of the secondary pipes so as to cover the whole area pf the project to the north and West of Greater Limassol.

·         Upgrading the most important installations on the system, such as the pumping station and the Moni Sewage Treatment Plant.

·         Carrying out anti-flooding works and expanding the storm drain system so as to put an end to the problem of flooding in certain areas.

Sewerage Projects – Phase 2b

The total cost of the sewerage projects that remain to be undertaken by 2018, including those in Phase 2b, is approximately €263 million.

The main Phase 2b projects are the following:

·         Expansion and upgrading of the central collecting pipe, which includes gravity and pressure pipes.

·         Expansion of the sewerage system so as to cover the whole of Greater Limassol. This entails extending the main and secondary pipes throughout the area of the completed project and includes all the problematic areas to the west and north of the existing system, such as the centre of Ayia Fyla and the Ekali and Ayios Athanasios areas.

It also includes the urban centres of the Kato Polemidia and Ayios Athanasios municipalities.

Construction work has finished for ten contracts (Ε1, Ε2, Ε3, Ε4, Ε5, Ε6, Ε7, Ε8, Ε12 and Ε16Α) and are underway for contract Ε9. 

Upgrading of the Moni Biological Wastewater Treatment Plant

The Biological Wastewater Treatment Plant reached full capacity in 2005 and so its expansion was deemed urgent.

Following the upgrading work, the plant’s maximum treatment capacity rose from 22,000 m3/day to 40,000 m3/day, while for an organic load it increased from 4,500 kg/day to approximately 15,000 kg/day.

Construction work on the expansion of the plant, costing approximately €30 million, began in August 2006 and finished in September 2008.

·         Upgrading pumping stations F, H, B, C, D and Ε so as to cope with the increased inflow of sewage from areas served by the system. Work on contract Ε11 for the upgrading of the pumping station is currently underway.

·         Construction of a new pumping station for the new areas being served by the system.

·         Construction of a new Wastewater Treatment Plant to the east of the 1st  Limassol Industrial Estate, with a capacity of 13,000m3/day.

Storm Drain ProjectsPhase 2b

Storm Drain Projects costing approximately €62 million are due to be implemented during Phase 2b. They include the following:

·         Construction of anti-flood works in western Limassol to resolve the problem of flooding in the area.

·         Construction of a storm drain network in densely populated areas of Limassol.

·         Construction of three rainwater tanks as part of Limassol’s anti-flood measures.

 

 

Ε-procurement KEPA
ep logo_nireas
LIFECAB Life-EBP