The sewerage and drainage project is constructed in phases and covers the entire urban Greater Limassol (Lemesos) area, which falls within the Sewerage Board of Limassol Amathus (SBLA) area, as defined by the Council of Ministers decrees. The construction works of Phase A of the sewerage and drainage system began in 1992 and were completed in 1995, while the works of the first stage of Phase B (Stage B1) which began in 1999, were completed in 2004.
Since1992, when the staged construction of the sewerage and drainage system began and up until 2005, over 137 million euro have been invested in the project. The works covered 50% of the (SBLA) area and about 12.000 premises have been connected to the sewerage system, providing service to about 100,000 people.
Currently, Phase B2 is being implemented and construction works continue to be carried out with our objective focusing on the expansion and completion of the works up to 2018. The works of the current phase began in August of 2006 with the expansion works of the Waste Wastewater Treatment Plant (WWTP) in Moni area. The above works have been completed in September 2008 and the new plant started to operate with a wastewater treatment capacity of 40,000 m3/day, compared to 20,000 m3/day treatment capacity, prior to the expansion.
The expanded WWTP contributed significantly in upgrading the environmental and hygienic conditions in the area and the enhancement of services provided and the satisfaction of the increasing needs of Greater Limassol Area. It has also relieved the city from the nuisance of disposal of domestic wastewater at the adjacent disposal site of “Vati”, which causes unpleasant odours and sewage overflows, with high environmental and health risks.
The storm water drainage works are also of a great importance and have to a great extent reduced the flooding problems in Greater Limassol Area. During the stage of Phase B2, storm water drainage works of about 50 km in total length are also scheduled to be constructed, expanding also to new areas, the cost of which amounts to about 32 million euro. Apart from these works, SBLA has prepared detailed designs and studies for the flood control system and storm water drainage works of the new link road of Limassol new port (vertical road) of estimated cost over 25 million euro, the entire cost of which will be borne by the Government. The project has started and is expected to be completed by 2018.
The main wastewater sewage works planned in the period between 2006-2013 are:
Storm water drainage works
The storm water drainage works planned for Phase B2 include the following:
Project Cost and Financing
The works described above consist the last phase (Phase B2) of the sewage and drainage system construction in Limassol (Lemesos) Greater Area and are expected to be carried out in fourteen or more contracts.
It includes the expansion of the wastewater sewage network, the expansion of the Waste Water Treatment Plant in Moni and other scheduled storm water drainage works including the construction of three storm water reservoirs.
The overall project cost until 2013 is expected to reach the aggregate cost of €340 million and it will be financed by a number of loans that the Board has secured under Government Guarantee, as follows:
Works and areas to be covered by Phase B2 of the Project
It is expected that the works for the current Phase B2 shall be executed under 14 or more contracts. The first contract for the expansion of the WWTP at Moni has been completed in September 2008, on a “Design, Build, Operate and Transfer” basis and put in operation. The sewerage and drainage network is scheduled to be expanded under 8 or 9 contracts.
Short description of the areas to be covered by the remaining contracts:
Contract E1
The area within the bounds of the Lemesos Municipality that is surrounded by Makarios avenue, Spyros Kyprianou avenue, Ayias Fylaxeos street and Garillis river, including the area around Nikou Pattichi street.
This Contract with a contract value of €14.293.267 has been signed in June 2008 and construction works began in September 2008. These works have been completed in September 2010.
In addition to the sewerage works, the construction of the storm water drainage works has been completed in the area of “Panayidis Foundation” and around the church of Ayia Varvara at Zakaki, which often suffers from serious flooding incidents due to the huge flow of storm water from the north suburbs. In addition, the storm water drainage works along Vasileos Konstandinou street has been constructed in the critical area south of “Tsirion” Stadium.
Contract E2
This contract with a contract value of €14.832.600 has already been signed and construction works began in March 2009. The expected completion date is June 2011.
The contract area includes the centre of the Ayios Athanasios Municipality, Kato Polemidia Municipality and the Ayia Fyla area east of “Ekali” and north of the Lemesos-Lefkosia bypass road.
Contract E3
This contract with a contract value of €15.768.001 has been completed in September 2009, approximately six months ahead of the contract date.
It covers the area that includes part of Zakaki, Ayios Ioannis and Omonoia and is surrounded by Garillis river, Spiros Kyprianou avenue, Pafos road, Miltonos, Serifou, Agaristis and Sarantoporou streets, Omonoia avenue and the Makarios avenue.
Contract E4
This contract with a contract value of €12.846.297 has also been signed and construction works have started and the expected completion date is February 2012.
It covers the area that includes the remaining of Zakaki area west of Miltonos street and up to the new link road leading to the Port. It also covers part of Kato Polemidia Municipality north of the First Industrial Area of Limassol and south of Pafos road.
Contract E5
This contract with a contract value of €9.923.000 was awarded early 2010 and construction works have started in June 2010.
It covers the area surrounded by Spiros Kyprianou avenue, the motorway, the Ayios Athanasios avenue and the Petrou Tsirou/Georgiou Papandreou streets, and the expected completion date is April 2012.
Contract E6
It covers the area surrounded by Spiros Kyprianou avenue, the motorway and west of the Petrou Tsirou and Georgiou Papandreou streets. This contract consists of substantial storm water drainage works and the total contract value is expected to exceed €25 million.
Contract E7
It covers the area surrounded by Spiros Kyprianou avenue, the motorway and west of the Marinou Geroulanou street. The area within the bounds of the Kato Polemidia Municipality east and south of the New Limassol General Hospital. The Government (self-housing) estate and the surrounding built-up areas in the Pano Polemidia Community.
Contract E8
It covers Ayias Fylaxeos parish area north of the motorway and Ekali area.
Contract E9
It covers “Panthea” area in the Mesa Geitonia municipality south of the new cemetery and up to the motorway, Ayios Athanasios municipality, Panioti area in Germasogeia municipality and the centres of the Communities of Palodia, Moutayiaka, Ayios Tichonas, Pyrgos and Parekklisia.
Contract E10
This contract includes the construction of the new pumping station Z and the construction of a second main collector connecting PSD with PSZ. The construction of pumping station M was cancelled.
Contract E11
This contract shall include the upgrading of the existing six pumping stations. It shall also include the installation of the SCADA system. Major expansion works are particularly expected at pumping station E.
Contract E12
This contract has been signed in September 2012 and includes the new twin force main collector that shall be constructed along the existing force main collector from Pumping Station F to the Moni WWTP of about 4 km length. The pipe laying contract shall cost about €3 million, whereas the pipe supply an additional amount of €3.5 million.
Contract E13
The results of the 2009 Master Plan Update, have shown that a new WWTP constructed in the West would better serve the West SBLA Area and would also improve the overall reliability of the system. This contract shall include the construction of a new wastewater treatment plant in the West part of Limassol of an estimated capacity of 15.000 m3/day with a significant part of the flow from the northern and western part of the system being diverted to it, thus relieving the coastal main collector and the existing eastern WWTP.
Tenders are expected to be invited by the end of 2010 and it is expected that the contract will be signed by mid 2011.
Contract E14
This contract provides for the rehabilitation of the coastal main collector, consisting of gravity mains and force mains.